CMS Pixel Detector Miscellaneous
Phase 1 Phase 2
Layer 1 Replacement Layers 2-4
  Layer 1 Replacement Elog  Not logged in ELOG logo
Message ID: 34     Entry time: Wed Nov 20 16:53:50 2019
Author: Andrey  
Category: Full test 
Subject: M1533 and M1534 FullQualification 
FullQualification of two modules M1533 and M1534 has been done. Full time of the test is about 7hrs.
Test included: FT@-10C, IV@-10, 2Cycles from -10C up to +10C, FT@-10C, IV@-10C, Ft@1-C and IV@10C.
No issues observed.
To be understood:
1) why SCurves results (noise) empty?
2) why the number of ROCs with defects always -1?