98
|
Mon Mar 9 16:16:48 2020 |
Andrey Starodumov | HDI test | HDIs: 3001, 3002, 3003, 3004 and 4033 | Today I tested 5 HDIs: 3001, 3002, 3003, 3004
and 4033
Results:
|
|
101
|
Wed Mar 11 17:12:05 2020 |
Matej Roguljic | HDI test | HDI testing procedure change | There is an additional test that will be used
from 11.03. on all HDIs. It involves measuring
the voltage between ground and the HV pin |
|
11
|
Wed Sep 18 15:45:45 2019 |
Matej Roguljic | Module assembly | HDI sparking under HV test | HDI [B]8010[/B] passed all test except the
HV. Under the HV test, some sparks could
be heard and even seen by eye on the right |
7x |
5
|
Wed Aug 7 11:49:07 2019 |
Matej Roguljic | Module assembly | HDI glue irradiation tests | Six different glues were used to glue the
cap on six dummy modules. They were all irradiated
to 120 MRad in Zagreb after which they were |
10x |
68
|
Thu Feb 6 17:09:50 2020 |
Dinko Ferencek | Module assembly | Gluing stamp improvements | Silvan has made additional grooves on the
gluing stamp which now sits stably on top
of the module without any rocking motion |
|
107
|
Sat Mar 14 17:08:14 2020 |
Matej Roguljic | Full test | Fulltests on 2020/03/13 |
Modules tested:
M1591 C (gain at -20)
|
|
94
|
Mon Mar 2 17:39:36 2020 |
Urs Langenegger | Full test | Fulltests on 2020/03/02 | Modules tested:
M1595 C
M1596 B
|
|
93
|
Fri Feb 28 17:33:16 2020 |
Urs Langenegger | Full test | Fulltests on 2020/02/28 | M1589 B
M1590 C (gain issues?)
M1591 C (noise issues?)
|
|
91
|
Thu Feb 27 09:47:51 2020 |
Urs Langenegger | Full test | Fulltest on 2020/02/26 | On Wednesday, 2020/02/26 the following modules
went through the full qualification procedure:
|
|
57
|
Thu Jan 30 13:51:03 2020 |
Matej Roguljic | Cold box tests | Fulltest failure - psiAgente | During the first fulltest@-20 of the full
qualification procedure for modules: 1539,
1541, 1542 and 1543; an error message popped |
|
79
|
Tue Feb 11 17:56:06 2020 |
Dinko Ferencek | Cold box tests | Fulltest failure - psiAgente | During today's full qualification the 2nd
fulltest@-20 for TB1 (M1562) failed
|
|
90
|
Wed Feb 26 10:34:55 2020 |
Urs Langenegger | Full test | Fulltest after Peltier replacement | On 2020/02/25, after SIlvan had replaced the
Peltiers, I did a fulltest. Here the summary:
|
|
261
|
Mon May 11 21:37:43 2020 |
Dinko Ferencek | Software | Fixed the BB defects plots in the production overview page | [URL=https://gitlab.cern.ch/CMS-IRB/MoReWeb/-/commit/0407e04c85725cac41a1cbf08af68744c40b2bc7]0407e04c[/URL]:
attempting to fix the BB defects plots in
the production overview page (seems mostly |
|
260
|
Mon May 11 21:32:20 2020 |
Dinko Ferencek | Software | Fixed double-counting of pixel defects in the production overview page | As a follow-up to this [URL=https://elrond.irb.hr/elog/Layer+1+Replacement/255]elog[/URL],
double-counting of pixel defects in the production
overview page was fixed in [URL=https://gitlab.cern.ch/CMS-IRB/MoReWeb/-/commit/3a2c67727b4b048c1546d666c4104396418bc2fe]3a2c6772[/URL]. |
|
265
|
Wed May 13 23:16:37 2020 |
Dinko Ferencek | Software | Fixed double-counting of pixel defects in the production overview page | [quote="Dinko Ferencek"]As a follow-up to
this [URL=https://elrond.irb.hr/elog/Layer+1+Replacement/255]elog[/URL],
double-counting of pixel defects in the production |
|
20
|
Wed Oct 2 12:41:16 2019 |
Dinko Ferencek | Module assembly | First production modules assembled | First production modules (M1530, M1531, M1532)
were built on Monday, Sep. 30 2019.
|
6x |
56
|
Mon Jan 27 17:50:48 2020 |
Matej Roguljic | Cold box tests | Failing modules at -20 | Friday, 24.1., it was noticed that the modules
are graded as 'C' in similar fashion. Module
is graded A/B at +10 degrees and then graded |
|
211
|
Tue Apr 14 17:19:44 2020 |
Andrey Starodumov | Full test | FT of M1668, M1669, M1670, M1672 | M1668: Grade B due to mean noise >200e for
several ROCs
M1669: Grade B due to ROC2 mean noise >200e
|
|
218
|
Thu Apr 16 17:31:16 2020 |
Andrey Starodumov | Full test | FT of M1662, M1675, M1676 | M1662: Grade C due to failure of ROC4 in almost
all tests: PixelAlive, PH calibration etc
Should be investigated and retested. At Reception |
|
206
|
Thu Apr 9 17:24:49 2020 |
Andrey Starodumov | Full test | FT of M1654, M1665, M1666, M1667 | M1654: Grade A
M1665: Grade B due to noisy pixels in ROC5.
To be checked by module doctor!
|
|