Entry  Thu Nov 28 15:58:20 2019, Matej Roguljic, General, Activities 26.-29.11.2019. 1-1.jpg1-2.jpg1-3.jpg1-4.jpg
26.11.

Prepared the tools for RD53A digital module assembly in the assembly lab
Entry  Thu Sep 26 17:38:07 2019, Matej Roguljic, General, Activities 25.-26.9. 
It was planned to test a batch of HDIs these 2 days but the shipment was late. Dinko and Andrei were shown the HDI testing procedure. Matej further worked
on the script used to test the HDIs. Dinko glued caps on 2 dummy modules and on M1522. New HDIs arrived on 26th and it looks like the kapton will have
to be put underneath them during the testing to prevent sparking.
Entry  Mon Jan 20 18:09:50 2020, Matej Roguljic, General, Activities 20.-31.01.2020. 
20.01.

Expanded the HDI testing setup to be able to mount wire-bonded HDIs to HDI handles. Tested 12 HDIs (v7.2), all of them passed the tests. HDIs were given
Entry  Tue Aug 6 15:15:00 2019, Matej Roguljic, General, Activities 19.6.-4.7.2019. 
17.6.-21.6.

Andrei and Matej were at PSI working on the cap gluing setup
Entry  Thu Sep 12 10:32:27 2019, Matej Roguljic, General, Activities 10.9.-19.9.2019. 
10.9.
Modules 1504,1505,1520 brought to PSI after irradiation to 1.2 MGy in Zagreb. All 3 were not working when put under test with pXar. 1504 and 1520 couldn't
set Vana at all. 1505 could set Vana, but timing couldn't be found and pixels weren't responding. Inspection under the microscope showed some "white-greenish"
    Reply  Thu Sep 19 14:20:07 2019, Matej Roguljic, General, Activities 10.9.-19.9.2019. 
[quote="Matej Roguljic"]10.9.
Modules 1504,1505,1520 brought to PSI after irradiation to 1.2 MGy in Zagreb. All 3 were not working when put under test with pXar. 1504 and 1520 couldn't
set Vana at all. 1505 could set Vana, but timing couldn't be found and pixels weren't responding. Inspection under the microscope showed some "white-greenish"
Entry  Tue May 19 13:43:55 2020, Andrey Starodumov, Module transfer, 9 modules shipped to PSI 
Quick check: Leakage current, set Vana, VthrCompCalDel and PixelAlive
Module    Current@-150V    Programmable     Readout
M1623    -0.335uA          OK               OK
Entry  Wed Feb 12 10:43:04 2020, Dinko Ferencek, Module transfer, 9 modules sent to ETH: 1539, 1545, 1547, 1548, 1549, 1550, 1551, 1552, 1553 
Yesterday the following modules were sent to ETH:
1539, 1545, 1547, 1548, 1549, 1550, 1551, 1552, 1553
Entry  Thu May 28 14:40:57 2020, Andrey Starodumov, Module transfer, 8 modules shipped to PSI 
Quick check: Leakage current, set Vana, VthrCompCalDel and PixelAlive
Module Current@-150V Programmable Readout
[COLOR=red]M1555 -6.000uA          OK          OK Current is rising up to 11uA with time after PixelAlive is done at +22C !!![/COLOR]
Entry  Mon May 18 14:05:01 2020, Andrey Starodumov, Module transfer, 8 modules shipped to ETHZ 
M1555, M1556, M1557, 
M1558, M1559, M1560,
M1561, M1564
Entry  Tue Mar 24 15:16:56 2020, Andrey Starodumov, HDI test, 8 HDIs tested on Mar 23 
1014, 1016, 2001, 2003, 
2004, 4013, 4015, 5014
All are good.
Entry  Mon Apr 6 17:07:23 2020, Andrey Starodumov, HDI test, 8 HDIs tested 
HDIs
4937 5043 5042 4040
2029 4019 4018 4017
Entry  Wed Mar 11 17:22:57 2020, Matej Roguljic, HDI test, 8 HDI tests on 11.3. 
I tested 8 HDIs today: 5029,5030,5031,6034,6036,6035,1031 and 1032
All of them tested fine.
Entry  Tue Feb 4 19:35:38 2020, Dinko Ferencek, Module transfer, 7 modules prepared for transfer to ETH: 1536, 1537, 1538, 1540, 1541, 1542, 1543 
The following modules have been prepared today for transport to ETH for x-ray qualification:
1536, 1537, 1538, 1540, 1541, 1542, 1543
Entry  Thu Mar 26 17:43:06 2020, Andrey Starodumov, HDI test, 6+1 HDI tested 
HDIs: 6021, 3014, 2005, 2009, 2006 and 2010 are OK
HDI 6024 failed: SDA0 and SDA2 on Ch1 missing
Entry  Thu Apr 2 17:08:03 2020, Andrey Starodumov, HDI test, 6 HDIs tested 
3013, 1046, 1047, 1048, 5038, 5039 are tested. All are OK.
Entry  Tue Apr 7 17:59:27 2020, Andrey Starodumov, HDI test, 6 HDIs tested 
HDIs
2030, 2031, 1021, 1022, 1023, 1035 
are tested. All OK.
Entry  Mon Feb 3 15:53:32 2020, Andrey Starodumov, Reception test, 5 modules RT: 1545, 1547, 1548, 1549, 1550 
[COLOR=blue]Feb 03[/COLOR]
- RT is done and OK for all modules. All 5 modules graded [COLOR=darkgreen]A[/COLOR].
Entry  Thu Mar 12 12:19:43 2020, Matej Roguljic, HDI test, 5 HDI tests on 12.3. 
I tested 5 HDIs on 12.3. 1030,1029,1040,1039 and 1038. 1039 failed all the electrical tests. All the others passed the tests. HDI 1038 has one wirebond
which is connected to the pad on the HDI and then it extends back up (like this: TBM./\.HDI/). The connection is good, but I just want to check with Silvan
later if this is a problem.
Entry  Wed Mar 25 18:30:23 2020, Andrey Starodumov, HDI test, 4+2 HDI tested 
2 suspicious HDIs retested and found OK: 5006/5007
5013, 5016, 3017, 3019 are OK.