Entry  Tue Feb 16 16:04:18 2021, Andrey Starodumov, General, POS calibrarion files created for L2 modules 
Following Dinko's instructions and after small modifications configuration files are created for modules:
BPix_BmI_SEC7_LYR2_LDR12F_MOD1.dat
BPix_BmI_SEC8_LYR2_LDR14F_MOD1.dat
BPix_BmO_SEC3_LYR2_LDR5F_MOD1.dat
BPix_BmO_SEC3_LYR2_LDR5F_MOD2.dat
BPix_BmO_SEC3_LYR2_LDR5F_MOD3.dat
BPix_BpO_SEC1_LYR2_LDR1F_MOD1.dat
BPix_BpO_SEC1_LYR2_LDR1F_MOD2.dat
BPix_BpO_SEC1_LYR2_LDR1F_MOD3.dat

The tar files are in /home/l_tester/L2L3_DATA/POS_files/Configuration_files directory

(keep in mind the message in https://elrond.irb.hr/elog/Layer+1+Replacement/303)
Entry  Fri Sep 11 14:48:39 2020, Matej Roguljic, Qualification, Qualification on 11.09. 
Four L2 modules were tested:

M2077 - B
M2197 - B
M2217 - B
M2232 - A
Entry  Fri Sep 11 12:00:02 2020, Matej Roguljic, Qualification, Qualification on 10.09. 
Four L2 modules were tested:

M2160 - A
M2355 - A
M2293 - A
M2298 - A

M2160 was retested since we suspected that poor HV contact caused it to be graded as C in its previous qualification (07.09.)
Entry  Fri Sep 11 11:57:37 2020, Matej Roguljic, Qualification, Qualification on 09.09. 
Four L2 modules were tested:

M2035 - B
M2036 - B
M2062 - A
M2155 - B
Entry  Wed Sep 9 11:23:29 2020, Matej Roguljic, Qualification, Qualification on 08.09. 
Four L2 modules were tested:

M2153 - C (IV@10)
M2258 - A
M2269 - A
M2278 - B (IV@10)
Entry  Tue Sep 8 10:28:08 2020, Matej Roguljic, Qualification, Qualification on 07.09. 
Four L2 modules were tested. The tests consist of Fulltest@-20, IV@-20, Temperature cycle (n=3), Fulltest@+10, IV@+10.
Modules tested:
M2026: A
M2078: A
M2126: A
M2160: C - this one is interesting since it's graded A at +10, but at -20 the results are horrible and we can see sensor wafer pattern.
Entry  Mon Sep 7 11:37:37 2020, Dinko Ferencek, Software, MoReWeb setup for L2-L3 modules  
A new branch called 'L2L3spares' was created in the MoReWeb repository that contains configuration modifications needed for testing L2 and L3 spare modules. All changes between the 'L2L3spares' branch and the default 'L1replacement' branch can be seen here.

Commands to run MoReWeb with the L2L3 setup are the following

cd /home/l_tester/L1_SW/MoReWeb/Analyse

git checkout L2L3spares (to switch to the 'L2L3spares' branch if not already on it)
python Controller.py -new


For going back to the L1 setup, one needs to run from inside a MoReWeb folder

git checkout L1replacement
Entry  Thu Sep 3 18:35:37 2020, Dinko Ferencek, Software, elComandante setup for L2-L3 modules 
A new branch called 'L2L3spares' was created in the elComandante repository that contains configuration modifications needed for testing L2 and L3 spare modules. All changes between the 'L2L3spares' branch and the default 'L1replacement' branch can be seen here.

Commands to run elComandante with the L2L3 setup are the following

cd /home/l_tester/L1_SW/elComandante/elComandante

git checkout L2L3spares (to switch to the 'L2L3spares' branch if not already on it)
python el_comandante.py -I FullQualificationL2L3.ini


For going back to the L1 setup, one needs to run from inside the elComandante folder

git checkout L1replacement
Entry  Thu Sep 3 16:22:12 2020, Dinko Ferencek, Software, pXar configuration for L2-L3 modules 
New sets of pXar configuration files were generated for L2 and L3 modules

cd /home/l_tester/L1_SW/pxar/main/

For L2

./mkConfig -d ../data/tbm09c -t TBM09C -r digv21respin -m

For L3

./mkConfig -d ../data/tbm08c -t TBM08C -r digv21respin -m

In both cases the Vcal value for the Trim test was changed from 50 to 35 in testParameters.dat. Finally, a copy of these folders was created

/home/l_tester/L1_SW/pxar/data/tbm08c_pxar/