CMS Pixel Detector Miscellaneous
Phase 1 Phase 2
Layer 1 Replacement Layers 2-4
  Layer 1 Replacement Elog, Page 10 of 16  Not logged in ELOG logo
ID Date Author Categorydown Subject Text Attachments
  168   Tue Mar 31 18:14:47 2020 Andrey StarodumovHDI test3 HDI testedHDIs: 1027, 5002, 5003 are tested. All OK.   
  174   Thu Apr 2 17:08:03 2020 Andrey StarodumovHDI test6 HDIs tested3013, 1046, 1047, 1048, 5038, 5039 are tested.
All are OK.
  
  184   Fri Apr 3 18:06:11 2020 Andrey StarodumovHDI test2 HDIs testedHDIs 6018 and 6019 are passed tests.   
  189   Mon Apr 6 17:07:23 2020 Andrey StarodumovHDI test8 HDIs testedHDIs
4937 5043 5042 4040
2029 4019 4018 4017
  
  194   Tue Apr 7 17:59:27 2020 Andrey StarodumovHDI test6 HDIs testedHDIs
2030, 2031, 1021, 1022, 1023, 1035 
are tested. All OK.
  
  208   Thu Apr 9 17:43:54 2020 Andrey StarodumovHDI test4 HDIa testedHDIs 3029, 3031, 3032, 4042 passed tests.
All OK.
  
  221   Mon Apr 20 17:09:12 2020 Andrey StarodumovHDI test4 HDIs testedAfter staying in 90%+ RH 2 HDIs became flat.
The first one was easy to mount on an HDI
holder.
  
  224   Wed Apr 22 17:28:42 2020 Andrey StarodumovHDI test11 HDIs testedAfter keeping HDIs in a very high RH for a
dew hours (24 is fine) became flat and could
be fixed on HDI holder by vacuum.
  
  229   Thu Apr 23 18:01:16 2020 Andrey StarodumovHDI test4 HDIs testedThe following HDIs are tested:
6007: OK
1034: Failed due to not working Channel 1
  
  230   Fri Apr 24 13:56:11 2020 Andrey StarodumovHDI test3 HDIs testedFollowing HDIs tested from the box "to be
understood":
5021, 3019, 5008. All are fine.
  
  234   Mon Apr 27 14:21:17 2020 Andrey StarodumovHDI test3 HDIs tested# remaining HDIs from "to be understood" box
were tested after flattening them during
weekend in RH=99.9% box.
  
  2   Tue Aug 6 15:15:00 2019 Matej RoguljicGeneralActivities 19.6.-4.7.2019.17.6.-21.6.

Andrei and Matej were at PSI working on the
  
  9   Thu Sep 12 10:32:27 2019 Matej RoguljicGeneralActivities 10.9.-19.9.2019.10.9.
Modules 1504,1505,1520 brought to PSI after
irradiation to 1.2 MGy in Zagreb. All 3 were
  
  13   Thu Sep 19 14:20:07 2019 Matej RoguljicGeneralActivities 10.9.-19.9.2019.[quote="Matej Roguljic"]10.9.
Modules 1504,1505,1520 brought to PSI after
irradiation to 1.2 MGy in Zagreb. All 3 were
  
  15   Thu Sep 26 17:38:07 2019 Matej RoguljicGeneralActivities 25.-26.9.It was planned to test a batch of HDIs these
2 days but the shipment was late. Dinko and
Andrei were shown the HDI testing procedure.
  
  18   Fri Sep 27 22:24:31 2019 Dinko FerencekGeneralActivities on 27. 9. 2019.[LIST]
[*] Today Silvan wire bonded TBMs to the
first batch of 8 new HDIs which were then
  
  27   Wed Oct 30 10:38:04 2019 Matej RoguljicGeneralActivities 28.-31.10.2019.28.10. - Investigated a problem with the FullQualification
setup, described more in this [URL=https://elrond.irb.hr/elog/Layer+1+Replacement/23]note[/URL]
29.10. - Further investigated the aforementioned
  
  38   Thu Nov 28 15:58:20 2019 Matej RoguljicGeneralActivities 26.-29.11.2019.26.11.

Prepared the tools for RD53A digital module
 1-1.jpg1-2.jpg1-3.jpg1-4.jpg 
  42   Fri Nov 29 17:06:26 2019 Dinko FerencekGeneralDropbox folder on CERNBox set upA dropbox folder for elComandante tar files
was set up in my CERNBox and synchronized
with the following local folder on the lab
  
  46   Mon Jan 20 18:09:50 2020 Matej RoguljicGeneralActivities 20.-31.01.2020.20.01.

Expanded the HDI testing setup to be able
  
ELOG V3.1.3-7933898