  63   Tue Feb 4 19:51:10 2020 Dinko FerencekModule assemblyCap gluingToday protective caps have been glued to modules
1545, 1547, 1548, 1549, and 1550.
  
  65   Wed Feb 5 16:07:03 2020 Dinko FerencekModule assemblyModule assembly spreadsheet migrated to Google SheetsExcel file stored on CERNBox containing the
module assembly spreadsheet has been replaced
with a Google Sheet [URL=https://docs.google.com/spreadsheets/d/12m2ESCLPH5AyWuuYV4KV1c5O_NEy7uP5PQKzVsdr3wQ/edit?usp=sharing]https://docs.google.com/spreadsheets/d/12m2ESCLPH5AyWuuYV4KV1c5O_NEy7uP5PQKzVsdr3wQ/edit?usp=sharing[/URL].
  
  68   Thu Feb 6 17:09:50 2020 Dinko FerencekModule assemblyGluing stamp improvementsSilvan has made additional grooves on the
gluing stamp which now sits stably on top
of the module without any rocking motion
  
  75   Sun Feb 9 12:05:47 2020 Dinko FerencekModule assemblyCap gluingToday protective caps have been glued to modules
1561 and 1562.
  
  85   Fri Feb 14 14:05:16 2020 Dinko FerencekModule assemblyProduction yield so farOf 41 modules produced and tested so far (1536-1576),
6 modules were found to be [COLOR=red]bad[/COLOR]
before or during the reception test, 5 were
  
  87   Mon Feb 24 13:53:32 2020 Urs LangeneggerModule assemblySetup changes in week 8Setup changes in week 8

Silvan considered the single-module gluing
  
  88   Mon Feb 24 14:01:29 2020 Urs LangeneggerModule assemblyCap gluing in W8In week 8 the following modules were glued
and tested: 
  
  89   Tue Feb 25 17:11:18 2020 Urs LangeneggerModule assemblyModules glued and tested Feb 24/25Modules glued and tested Feb 24/25

The letters after the module name indicate
  
  110   Mon Mar 16 15:17:18 2020 Matej RoguljicModule assemblyM1601 and M1602Andrey and I assembled modules 1601 and 1602
on Friday, 13.3. On Monday, 16.3. I ran reception
on them (both graded A) and then glued protection
  
  114   Wed Mar 18 17:43:41 2020 Andrey StarodumovModule assemblyM1605-M1608M1605 and M1606: reception done on Mar 17
M1607 and M1608: reception done today
All: grade A
  
  98   Mon Mar 9 16:16:48 2020 Andrey StarodumovHDI testHDIs: 3001, 3002, 3003, 3004 and 4033Today I tested 5 HDIs: 3001, 3002, 3003, 3004
and 4033
Results:
  
  101   Wed Mar 11 17:12:05 2020 Matej RoguljicHDI testHDI testing procedure changeThere is an additional test that will be used
from 11.03. on all HDIs. It involves measuring
the voltage between ground and the HV pin
  
  102   Wed Mar 11 17:22:57 2020 Matej RoguljicHDI test8 HDI tests on 11.3.I tested 8 HDIs today: 5029,5030,5031,6034,6036,6035,1031
and 1032
All of them tested fine.
  
  104   Thu Mar 12 12:19:43 2020 Matej RoguljicHDI test5 HDI tests on 12.3.I tested 5 HDIs on 12.3. 1030,1029,1040,1039
and 1038. 1039 failed all the electrical
tests. All the others passed the tests. HDI
  
  121   Fri Mar 20 18:09:47 2020 Andrey StarodumovHDI test3 HDIs tested5008 failed, but most likely die to the pin
head mis-alignment. Test to be repeated.
5007 and 5008: passed tests but during HV
  
  126   Tue Mar 24 15:16:56 2020 Andrey StarodumovHDI test8 HDIs tested on Mar 231014, 1016, 2001, 2003, 
2004, 4013, 4015, 5014
All are good.
  
  138   Wed Mar 25 18:30:23 2020 Andrey StarodumovHDI test4+2 HDI tested2 suspicious HDIs retested and found OK: 5006/5007
5013, 5016, 3017, 3019 are OK.
  
  145   Thu Mar 26 17:43:06 2020 Andrey StarodumovHDI test6+1 HDI testedHDIs: 6021, 3014, 2005, 2009, 2006 and 2010
are OK
HDI 6024 failed: SDA0 and SDA2 on Ch1 missing
  
  149   Fri Mar 27 14:32:11 2020 Andrey StarodumovHDI testList of suspicious HDIsHere are HDIs that the first time tested showed
500-600V measured on the pin or directly
on the HDI pad instead of 800V:
  
  159   Mon Mar 30 17:40:35 2020 Andrey StarodumovHDI test3+2 HDIs (re-)testedFor 3 HDIs: 3014, 3017, 6021, HV has been
re-measured. In all cases 790V is measured
with 800V supplied.
  