  3   Tue Aug 6 16:01:17 2019 Matej RoguljicSoftwareWrong dac settings - elComandanteIf it seems that elComandante is taking wrong
dac settings for tests like Reception test
or full qualification, one should remember
  
  4   Tue Aug 6 16:06:45 2019 Matej RoguljicOtherVsh and ctrlreg for v4 chipsThe recommended default value for Vsh is 8,
but the current version of pXar has it as
30. One should remember this when making
  
  5   Wed Aug 7 11:49:07 2019 Matej RoguljicModule assemblyHDI glue irradiation testsSix different glues were used to glue the
cap on six dummy modules. They were all irradiated
to 120 MRad in Zagreb after which they were
 10x 
  6   Wed Aug 7 12:24:14 2019 Matej RoguljicDocumentationActivities 31.7.-9.8.2019.31.7.

Matej tested 4 HDIs (8030-8033 and 8010).
  
  7   Wed Aug 7 18:01:06 2019 Matej RoguljicCold box testsPhOptimization problemAugust 7 - we found out that PhOptimization
algorithm starts leaking memory if it fails
to find proper values. If running one setup,
  
  8   Tue Sep 10 15:18:20 2019 Matej RoguljicOtherModules 1504, 1505, 1520 irradiation reportModules 1504, 1505 and 1520 were taken to
Zagreb for irradiation on 13.08.19. The goal
was to check the v4 behavior after irradiation.
  
  9   Thu Sep 12 10:32:27 2019 Matej RoguljicGeneralActivities 10.9.-19.9.2019.10.9.
Modules 1504,1505,1520 brought to PSI after
irradiation to 1.2 MGy in Zagreb. All 3 were
  
  11   Wed Sep 18 15:45:45 2019 Matej RoguljicModule assemblyHDI sparking under HV testHDI [B]8010[/B] passed all test except the
HV. Under the HV test, some sparks could
be heard and even seen by eye on the right
 7x 
  13   Thu Sep 19 14:20:07 2019 Matej RoguljicGeneralActivities 10.9.-19.9.2019.[quote="Matej Roguljic"]10.9.
Modules 1504,1505,1520 brought to PSI after
irradiation to 1.2 MGy in Zagreb. All 3 were
  
  15   Thu Sep 26 17:38:07 2019 Matej RoguljicGeneralActivities 25.-26.9.It was planned to test a batch of HDIs these
2 days but the shipment was late. Dinko and
Andrei were shown the HDI testing procedure.
  
  23   Mon Oct 28 17:01:05 2019 Matej RoguljicSoftware Investigating the bug with the Keithley clientWe took module 1529 and tried recreating the
issue observed in the beginning of October.
To do this in a reasonable amount of time,
  
  25   Tue Oct 29 16:36:23 2019 Matej RoguljicModule assemblyAssembly lab cap gluing jigsThere are two jigs for cap gluing in the assembly
lab, circled in red and blue on the photo
in the attachment. The one closer to the
 IMG_20191029_150037.jpg 
  26   Tue Oct 29 16:38:32 2019 Matej RoguljicSoftware Investigating the bug with the Keithley client[quote="Matej Roguljic"]We took module 1529
and tried recreating the issue observed in
the beginning of October. To do this in a
  
  27   Wed Oct 30 10:38:04 2019 Matej RoguljicGeneralActivities 28.-31.10.2019.28.10. - Investigated a problem with the FullQualification
setup, described more in this [URL=https://elrond.irb.hr/elog/Layer+1+Replacement/23]note[/URL]
29.10. - Further investigated the aforementioned
  
  30   Wed Oct 30 16:54:58 2019 Matej RoguljicSoftware Investigating the bug with the Keithley client[quote="Matej Roguljic"][quote="Matej Roguljic"]We
took module 1529 and tried recreating the
issue observed in the beginning of October.
  
  31   Thu Oct 31 10:41:12 2019 Matej RoguljicCold box testsIssue with DTB_WWVASWOn 29th of October, an issue with DTB_WWVASW
was noticed when trying to run FullQualification
on 4 modules at the same time. On a tested,
  
  35   Wed Nov 27 08:39:24 2019 Matej RoguljicCold box testsBump bonding test investigationThe BB test on M1534 shows a lot of dead bunmps
on C10 and some on C1 and C0 as well. Putting
a source on top of the module shows that
  
  38   Thu Nov 28 15:58:20 2019 Matej RoguljicGeneralActivities 26.-29.11.2019.26.11.

Prepared the tools for RD53A digital module
 1-1.jpg1-2.jpg1-3.jpg1-4.jpg 
  46   Mon Jan 20 18:09:50 2020 Matej RoguljicGeneralActivities 20.-31.01.2020.20.01.

Expanded the HDI testing setup to be able
  
  56   Mon Jan 27 17:50:48 2020 Matej RoguljicCold box testsFailing modules at -20Friday, 24.1., it was noticed that the modules
are graded as 'C' in similar fashion. Module
is graded A/B at +10 degrees and then graded
  